Hi there, We are planning to expand our 3par 7200 (1s+1L) with one S (6710) cage online without any shutdown or interrupt.Would you please help me ? |
Author: | cali [ Thu Sep 28, 2017 4:31 am ] |
Post subject: | Re: Adding cage to 3par7200 online |
Sure. Should I came On-Site? Anyway, look for this Dokument: HP 3PAR StoreServ 7000 Series Storage Cabling Configuration Guide C Two Node System with Mixed M6710+M6720 Enclosures.pdf |
Author: | ehsankhayyat [ Thu Sep 28, 2017 12:50 pm ] |
Post subject: | Re: Adding cage to 3par7200 online |
Hi Cali, I have read this document before.But I did not find any step by step useful guide to add cage online.would you please say what page do you mean ? thanks. |
Author: | cali [ Thu Sep 28, 2017 1:49 pm ] |
Post subject: | Re: Adding cage to 3par7200 online |
You have only one Cage. So DP-1 Port on the Controller is free. - add License - set Maintenance Mode on the SP (this is for HPE Only) - Power on the Shelf (Drives inserted) - Connect SAS Cable as in the Manual (One Cable is longer as the other, you need this for next expansion) - admithw |
Author: | ehsankhayyat [ Fri Sep 29, 2017 1:47 am ] |
Post subject: | Re: Adding cage to 3par7200 online |
Dear Cali, as I said before I have 2 cage , one 6710 and one 6720 and I want to add one 6710 cage as expansion.So all DP port on node 0 and node 1 were used before. thanks. |
Author: | cali [ Fri Sep 29, 2017 2:33 am ] |
Post subject: | Re: Adding cage to 3par7200 online |
So you have a Short Red Cable that going from Node 0 Top to Down. And a Long Green Cable going from Node 1 Down to Up. Prepare as I describe. Label the two new short Cables as in the Manual. Follow the Manual. Figure 24 Reviewing Controller Node 0 Cable Connections Add the new Shelf in the Data Path by connecting a new short Red Cable that goes from E1 DP-2 to E3 DP1. Wait for Discovery. Check twice. Dont put in the unlabeld Port! Use: checkhealth cabling Now you disrupting one Path, this needs that the Red Path is fine. Now: Figure 29 Reviewing Controller Node 1 Cable Connections Move the Long Green Cable from E1 DP-1 to E3 D-1. Add a short Green Cable from E3 DP-2 to E1 DP-1. Use: checkhealth cabling You can also use the command "servicecage guidecabling" for assistance. |
Author: | ehsankhayyat [ Mon Oct 02, 2017 3:29 am ] |
Post subject: | Re: Adding cage to 3par7200 online |
Hi Cali,thank you for paying attention. |